Anthropic reportedly lost $80.7bn in the first half of 2026, according to The Wall Street Journal, which first reported the figure on 20 October from a draft prospectus it viewed, and Reuters, which reviewed the draft separately. Reuters reported that about $72bn of that loss was an accounting charge tied to bonds that could convert into Anthropic shares, not cash spent running the business.
Shares in the cloud companies that rent out AI chips, often called neoclouds, have also fallen this month. CoreWeave closed at $54.235 on 23 October, down about 41% from its 6 October close, and Nebius fell about 36% to $158.74 over the same days, by Polstob's calculation from Nasdaq closing prices. The declines began before the WSJ report, and Polstob found no report or filing tying them to Anthropic's figures.
| Item | Reported figure | Reported by, and basis |
|---|---|---|
| Net loss, H1 2026 | $80.7bn (H1 2025: $13bn) | WSJ and Reuters, each citing a draft prospectus it saw; H1 2025 figure from Reuters |
| Accounting charge on convertible bonds and other financing | About $72bn | Reuters, citing the draft; WSJ, as summarised by Stocktwits |
| Revenue, H1 2026 | $16.3bn (H1 2025: $1.1bn) | WSJ, citing the draft, as summarised by Stocktwits |
| Compute and infrastructure spending, H1 2026 | Nearly $9bn (H1 2025: $2.3bn) | Reuters, citing the draft |
| Cloud, computing and infrastructure commitments | At least $518bn over a decade, about 80% non-cancelable or payable regardless of usage | Reuters, 29 September, citing the confidential prospectus |
| Potential computing spend, including deals under negotiation | Up to $750bn | WSJ, citing the draft |
| Net loss, 2025 | About $42bn, including a charge of roughly $34bn | Reuters, 28 September, citing the prospectus |
| Revenue, Q3 2026 | $16.8bn, up 45% on Q2 | Reuters, citing people familiar with a 14 October investor meeting |
Source: WSJ (20 October 2026), Reuters (28-29 September and 20 October 2026) and a Stocktwits summary of the WSJ report; not a public filing and not confirmed by Anthropic, Reported 28 September to 20 October 2026. Polstob has not seen the draft prospectus. The exact name of the accounting line behind the roughly $72bn charge will only be known once a registration statement is public.
The view being tested
Andreas Steno Larsen of Steno Research has argued on X that markets misread the loss. Quoting on 21 October a post that set the $80.7bn loss next to $16.3bn of revenue, he asked whether people had looked into the figure and wrote: "It is a non-cash item due to the appreciation of the value of the company". Earlier that day he posted a Steno Research chart whose title describes the first half as an $81bn loss that is in effect a $1bn loss. That $1bn figure is his own estimate, and the chart says its components are approximate.
“Excluding fair-value changes (which are non-cash items), they’re approaching break-even fast.”
He sees supply, not demand, as the limit. On 20 October he answered the WSJ's $750bn figure with "They are capacity constrained and will buy more hardware", and on 21 October he wrote that "OpenAI is eating up market share. The reason? OpenAI has the capacity. Anthropic doesn’t." He has also flagged risk at the neoclouds: on 14 October he wrote that several of them "have locked in the income side on contracts, but have open risk on building costs and financing costs, which are going up".
Where the reported numbers back him
Reuters reported that the draft describes the roughly $72bn as reflecting a higher estimated value of bonds that could later turn into shares, rather than operating cash costs, and Steno's chart uses the same figure. The mechanism, in general terms: when a company's estimated value rises, instruments that can convert into its shares become worth more, and accounting rules record that increase as a loss although no cash leaves the company. The cost is real but falls elsewhere, as extra shares for those holders when they convert, which dilutes other shareholders. Reuters reported a similar pattern for 2025: a net loss of about $42bn that included a charge of roughly $34bn.
Revenue has also outpaced spending on computing. The WSJ put first-half revenue at $16.3bn against $1.1bn a year earlier, according to a Stocktwits summary of its report, while Reuters put compute and infrastructure spending at nearly $9bn against $2.3bn. The Financial Times reported on 14 October, citing people familiar with the matter, that Anthropic told investors it generated $1.70 in revenue per $1 of computing spend in the third quarter and was cash-flow positive, according to an Investing.com summary of the FT report.
Anthropic itself describes strain on capacity. On 20 April it wrote that "Growth at this pace places an inevitable strain on our infrastructure" and committed more than $100bn over ten years to AWS for up to 5GW. It has also signed a multi-gigawatt TPU deal with Google and Broadcom and, per its Series H announcement of 28 May, access to GPU capacity at SpaceX's Colossus sites. Reuters reported that the draft expects demand to be "limited principally by the availability of compute." One neocloud contract is public: the Form S-1 of Nscale, filed on 18 September, shows 25 August 2026 agreements worth up to about $44.6bn to Nscale for dedicated NVIDIA Vera Rubin capacity.
Where the reported numbers do not back him
Not all of the reported $80.7bn was non-cash. On the figures Reuters reported, about $8.7bn of the first-half loss sits outside the $72bn charge, by Polstob's arithmetic (80.7 minus 72), and the reports Polstob could read do not break that remainder down. Polstob found no news report of a first-half operating loss near the $1bn shown in Steno's chart. The profit Anthropic described to investors was on an adjusted basis, according to the FT and CNBC reports; that measure has not been defined publicly.
Growth has slowed. CNBC, citing people familiar with the matter, put revenue at $4.7bn in the first quarter, $11.6bn in the second and $16.8bn in the third; Reuters, citing people familiar with the 14 October meeting, reported the same second- and third-quarter figures. Reuters reported that the slower sequential rate disappointed some investors. Steno's view that capacity, not demand, explains the slowdown is his interpretation; no filing or report establishes it.
Nor does Anthropic's demand pass straight through to neocloud shares. Neither CoreWeave's second-quarter 10-Q nor Nebius's second-quarter results filings name Anthropic as a customer. According to Reuters, citing the prospectus, Anthropic's long-term obligations over seven to ten years include at least $111.1bn to Google, $110bn to Amazon and $31.4bn to Microsoft, on top of roughly $161.2bn in equipment leases linked to Broadcom that are mostly non-cancelable. Its xAI agreements, worth up to $84.5bn, can mostly be ended at 90 days' notice, Reuters reported. The Stocktwits summary of the WSJ report puts commitments for renting NVIDIA chips through smaller providers such as Nscale and Lambda at $86bn.
| Item | CoreWeave | Nebius |
|---|---|---|
| Revenue, Q2 2026 | $2,575m (Q2 2025: $1,212m) | $582.3m (Q2 2025: $105.1m) |
| Remaining performance obligations, 30 June 2026 | $103.7bn | $37.5bn |
| Capital spending, H1 2026 (cash) | $14.1bn | $8.13bn |
| Interest expense | $640m net in Q2 (Q2 2025: $267m) | $182.8m in H1 (H1 2025: $4.8m) |
| Largest customers, share of Q2 revenue | 36%, 26% and 10% | 24%, 21% and 14% |
| Recent financing | $3.7bn of 2.875% convertible notes due 2033 (September) | $5.75bn of convertible notes (August); $3.5bn senior secured Citi facility (22 October) |
| Server useful life | Risk factor warns its estimates may prove inaccurate | Raised to five years from four from Q1 2026 |
Source: CoreWeave Form 10-Q and Forms 8-K; Nebius Group Forms 6-K (2026), Q2 or H1 2026; financing as announced. Nebius capital spending is purchases of property, equipment and intangible assets. CoreWeave reports interest expense net of capitalized interest; Nebius reports interest expense separately from interest income, for a six-month period.
CoreWeave's 10-Q shows total indebtedness of $35.6bn at 30 June 2026, with $10.0bn undrawn. On its 11 August earnings call, the company guided 2026 capital spending of $35bn to $39bn and third-quarter interest expense of $860m to $940m. Chief financial officer Nitin Agrawal said on the call that the cost of a contract is "front loaded, requiring a combination of debt, customer prepayments and other corporate level capital to finance its build out."
NVIDIA supplies all of CoreWeave's GPUs and bought $2.0bn of its stock in January 2026. A loan announced on 10 August runs about five years while the contracts behind it average about three; CoreWeave said this shows lenders are willing to underwrite renewal risk.
Nebius's 12 August Q2 shareholder letter says it expects over $9bn of customer prepayments in 2026 and calls capacity a binding constraint on AI adoption. Its management discussion shows it lengthened the useful life of server and network equipment to five years from four from the first quarter of 2026, which lowers the annual depreciation charge; Nebius said the change reflects usage patterns and current utilization commitments. Its first-quarter letter cites an equity investment from NVIDIA. Nscale's S-1 says it has not secured binding commitments for any of the financing needed to deliver the Anthropic contract, that Anthropic may end a tranche without liability if delivery is late, and that it expects Microsoft and Anthropic to be significant customers.
The bear case
- Financing: CoreWeave's quarterly net interest expense more than doubled year on year to $640m in Q2, Nebius has added convertible notes and a secured loan, and Nscale's S-1 says it had no binding financing commitments for its Anthropic build.
- Concentration: at both CoreWeave and Nebius, three customers made up more than half of Q2 revenue; Reuters reported that two customers gave Anthropic nearly a quarter of its 2025 revenue.
- Investor-supplier ties: NVIDIA is supplier and shareholder at CoreWeave; Microsoft and NVIDIA have pledged investments in Anthropic.
- Reuters reported that the prospectus says Amazon, Google and Microsoft, as investors and cloud providers, have incentives that "may not be fully aligned" with Anthropic's.
- Asset lives: longer useful-life estimates lower the annual depreciation charge now and hold up only if older chips keep earning; Steno wrote on X on 25 October that "Every single GPU bought since 2021 has far outrun its depreciation cost, and it remains the case by miles." The post did not include supporting data.
- Take-or-pay: non-cancelable commitments give suppliers visibility but become a fixed cost for Anthropic if growth slows, and Reuters reported that the company must pay Google any shortfall in its committed spending.
- Anthropic, 'Anthropic confidentially submits draft S-1 to the SEC' (1 June 2026), 1 Jun 2026, 02:00 CEST
- The Wall Street Journal, 'Anthropic S-1 Shows Red-Hot Growth, Risks and Massive Computing Costs' (draft prospectus viewed by the Journal), 20 Oct 2026, 21:30 CEST
- Reuters, 'Anthropic logged net loss of over $80 billion in first half of 2026' (draft prospectus reviewed by Reuters; via StreetInsider), 20 Oct 2026, 21:40 CEST
- CoreWeave, Inc., Form 10-Q for the quarter ended 30 June 2026, 12 Aug 2026, 01:24 CEST
- Nebius Group N.V., Form 6-K, Q2 2026 results (12 August 2026), 12 Aug 2026, 02:00 CEST